Automatic Cz Purlin Roll Forming Machine

Introduction of cz purlin roll forming machine CZ purlin roll forming machine is to produce light steel main equipment, the use of steel or steel cold-formed after forming...

Send Inquiry
Product Details

Automatic Cz Purlin Roll Forming Machine

Product details

C/Z purlin of C/Z purlin roll forming machine according to different height is divided into 80, 100, 120, 140, 160, five kinds of specifications, the length can be according to the engineering design and determined, but considering the transportation and installation conditions, generally not more than 12 miles in length.


Introduction
CZ purlin roll forming machine is to produce light steel main equipment, the use of steel or steel cold-formed after forming, rolling production models of a variety of specifications purlins finished.
The thickness of the product out of the apparatus can be made very thin, but also greatly simplifies the production process, improve production efficiency. Wall thickness can be produced hot-rolled with the general method but difficult to produce a uniform cross-sectional shape of the complex variety of profiles and cold-formed steel of different materials.


Specification
1). Width & Height & Thickness of sheet: According to Drawings
2). Material: GI sheet coil or Colored sheet coil
3). Motor Power: 5.5 kw forming system
4). Roller material:Cr12.
5). Surface of Roller: Heat treatment HRC58-60.
6). Diameter of main shaft: 60mm #45 steel, heat treat modulation
7). Forming station: 12 stations.
8). Transmission: by chain and gear
9). Measuring accuracy: +/- 0.5 mm/M.
10). Safety Hood: Cage
11). Arch middle plate: 30mm thickness.
12). Output: 8-10 Tons per shift (8 hrs.).
13). The machine base is assembled and welded by high quality steel.


Picture of C/Z purlin roll forming machinepurlin machine .jpg


After sale services

a). Engineer will give free training lessons to labors in buyer’s factory.

b). Buyer will buy the round-trip air ticket for Engineer if visa application is approved. The buyer is also responsible to bear expenses generated, e.g. visa formalities, meals, accommodation and allowance of USD80 for engineer.

c). During this guarantee period, we will provide spare parts without any charge in case of quality discrepancy caused by us. If the malfunctions are caused by your incorrect operations, we will provide the buyer spare parts at cost price.

d). We will charge the buyer cost price of spare parts beyond one year and provide long-term technical guide.